Uzbek Metallurgical Plant expected to become HRC's self-sufficient supplier in 2021

11 Jul 2019 17:07 reported by Raul Lee

A A A
It was reported that the Uzbek steelmaker of long steel products, Uzbek Metallurgical Plant, would start constructing the hot-rolled coils (HRC) mill this year, aiming to become a self-sufficient supplier when the new mill started to operate in 2021.

The new mill was capable to produce coils with a thickness between 1.4mm and 12mm and a width between 800mm and 1,300 mm.

The planned production capacity was 1 million metric tons per year. Also, the Italian engineering company Danieli will supply equipment for the new mill.

Back to Steel News

Related News

NALCO forced to shut down 80 electrolytic cells

  • Industry activities
  • 22 Oct 2019 15:54

Turkey's Kardemir launches new investment plan

  • Industry activities
  • 22 Oct 2019 11:33

Tata Steel to cut 2,500 jobs in Europe

  • Industry activities
  • 22 Oct 2019 11:08

Turkish Ataer Holding to complete acquisition of British Steel in Nov

  • Industry activities
  • 21 Oct 2019 16:31

Linggang's new 120-ton converter for capacity replacement

  • Industry activities
  • 21 Oct 2019 16:10

Metal Price Index

Learn more

LME Official Bid Price

  • Zinc
  • 2,499.00
  • 2,474.00
  • Aluminum
  • 1,735.00
  • 1,741.00
  • Copper
  • 5,818.00
  • 5,842.00
  • Nickel
  • 16,190.00
  • 16,190.00

Learn more

Coil Exchange Center

  • 2B Coil-Nov
  • 2,680
  • 2,540
  • NO1 Coil-Nov
  • 2,630
  • 2,490
  • 2B Coil-Nov
  • 2,680
  • 2,540
  • NO1 Coil-Nov
  • 2,630
  • 2,490

Learn more